Project Overview

Wattle Creek BESS · Connection approval status & pipeline

Viewing as Consultant — full technical access

Submission Readiness

pre-lodgement
72/ 100
2 blocking items Clear blockers to reach 90%+

Time in Stage

TDD Round 2
23days
vs benchmark 18 days for grid-forming BESS
5 days over benchmark

AEMO 60-Day Clock

status notification
41days left
Statutory notification due 17 Jul 2026
On track

Connection Pipeline

6-stage AEMO process
  1. Connection Enquiry
    Transgrid · scope confirmed
    14 Mar 25
  2. GPS Negotiation
    Access standards agreed · ERC0393
    02 Sep 25
  3. R1 Submitted
    GPS v3.0 + DMAT + models lodged
    28 Mar 26
  4. TDD Round 1
    12 issues raised · all resolved
    06 May 26
  5. TDD Round 2
    4 issues open · 2 blocking
    in progress
  6. R1 Acceptance
    Model accepted → registration
    pending

Recent Activity

AEMO
raised TDD Round 2 issue #R2-2 (active power recovery)
2h ago
C. Nguyen
uploaded GPS Document v3.2
2h ago
Sungrow
confirmed model v3.1.4 clears the v3.1.2 DLL issue
1d ago
Transgrid
resolved issue #R2-3 (fault level)
2d ago
You
ran pre-submission audit — 2 blocking items found
2d ago