Project Overview
Wattle Creek BESS · Connection approval status & pipeline
Viewing as Consultant — full technical access
Submission Readiness
pre-lodgement72/ 100
2 blocking items Clear blockers to reach 90%+
Time in Stage
TDD Round 223days
vs benchmark 18 days for grid-forming BESS
5 days over benchmark
AEMO 60-Day Clock
status notification41days left
Statutory notification due 17 Jul 2026
On track
Connection Pipeline
6-stage AEMO process- ✓Connection EnquiryTransgrid · scope confirmed14 Mar 25
- ✓GPS NegotiationAccess standards agreed · ERC039302 Sep 25
- ✓R1 SubmittedGPS v3.0 + DMAT + models lodged28 Mar 26
- ✓TDD Round 112 issues raised · all resolved06 May 26
- ●TDD Round 24 issues open · 2 blockingin progress
- ○R1 AcceptanceModel accepted → registrationpending
Recent Activity
AEMO
raised TDD Round 2 issue #R2-2 (active power recovery)
2h ago
C. Nguyen
uploaded GPS Document v3.2
2h ago
Sungrow
confirmed model v3.1.4 clears the v3.1.2 DLL issue
1d ago
Transgrid
resolved issue #R2-3 (fault level)
2d ago
You
ran pre-submission audit — 2 blocking items found
2d ago